Other implementation
-
Loading station for NaOH and H2SO4
Slovak sugar factory, s.r.o.
Execution.
Year of implementation: 2016
Investment costs: 340 000 €
-
Applicator PZ4
Bekaert Slovakia s.r.o.
Project + complete execution.
Year of implementation: 2018
Investment costs: 129 000 €
-
Expansion of HCl tankpark
Bekaert Slovakia s.r.o.
Project for execution.
Year of implementation: 2016
Investment costs: 16 000 €
-
Dosing of CUMAR solution
Bekaert Slovakia s.r.o.
Project for execution + complete execution.
Year of implementation: 2016
Investment costs: 35 000 €
-
Loading and storage station for concentrate of HNO3 and NaOH
RAJO, a.s.
Project for building licence and for execution.
Year of implementation: 2015
Investment costs: 21 000 €
-
Relocation of PMO to Pálenisko basin
SPaP, a.s.
Delivery of the Double wall safety pipeline BRUGG-STAMANT.
Year of implementation: 2010
Investment costs: 440 000 €
-
Road car tank unloading area modification
Johns Manville Slovakia, a.s.
Documentation for the Building permit.
Year of implementation: 2009
Investment costs: 19 900 €
-
Intenzifikation of the hydrogenation feed pumps
Sloveca, a. s.
Project and modification of the existing pumps for ethylenoxid and propylenoxid.
Year of implementation: 2008
Investment costs: 92 000 €
-
Modernizing of oil storage system
Transpetrol, a.s.
Realization project, delivery of machine and technological part, measurement and control part.
Year of implementation: 2008
Investment costs: 49 000 €
-
Tires treating factory
DRON Agro, s.r.o.
Delivery of 20 pcs Johnson Pump, typ CombiBloc, technical consulting.
Year of implementation: 2007
Investment costs: 43 000 €
-
Liquefaction unit of petrol steam
OKTAN Kežmarok
Project for the construction permit and realization with utilize of Borsig technology, delivery of the pump.
Year of implementation: 2007
Investment costs: 30 500 €
-
Varnish regeneration unit
Hella Slovakia Front Lighting, s.r.o.
Realization project, development and delivery of the unit.
Year of implementation: 2007
Investment costs: 71 000 €
-
Overloading of discharge pipelines in terminal Slovnaft - Horný Hričov
Doprastav, a.s.
Delivery and installation of safety pipelines Brugg Stamant, leak detection system.
Year of implementation: 2007
Investment costs: 3 177 000 €
-
Utilization of geothermal water in Zlatná na Ostrove
4 Fruit, s.r.o.
Realization project, delivery of inhibitor spray.
Year of implementation: 2006
Investment costs: 39 800 €
-
Transport of high viscouse suspensions
Zentiva, a.s.
Delivery of 4 pcs rotary piston pump Johnson Pump, typ TopLobe.
Year of implementation: 2005
Investment costs: 49 800 €
-
Transport of sulfuric acid 96%
Glass factory Poltár
Delivery of flexible piping Brugg, leak indication system.
Year of implementation: 2005
Investment costs: 71 000 €
-
Device for medium pressure holding of decorating machine
Chemosvit Svit, a.s.
Suggestion, documentation and delivery of the complete medium pressure holding device by utilization of the Wilden pump.
Year of implementation: 2005
Investment costs: 29 900 €
-
Distribution of mediums in varnish room
KIA Slovakia, a.s.
Detail engineering of pipelines in the varnish room for the company Dür (Germany).
Year of implementation: 2005
Investment costs: 29 900 €
-
Tires conveyer belts system
Continental Púchov
Construction project.
Year of implementation: 2004
Investment costs: 10 000 €
-
Storage and loading system of Methanol into the furnaces
SACHS Trnava
Delivery of dosing pumps, unloading hoses with self-seal quick couplings TODO, level measurement LABKO for transport containers.
Year of implementation: 2003
Investment costs: 145 000 €
-
Methanol storage unit
INA Kysuce, a.s.
Delivery of pneumatic pumps, leak detection system of double wall storage vessels and level sensor system .
Rok realizácie: 2002
Investičné náklady: 45 700 €
-
Storage facility of turbine-compressor oil (Slovakia)
SPP, a.s.
Flexible double-wall piping Brugg Rohrsystem, leak detection system SGB and level sensors LABKO.
Rok realizácie: 1997
Investičné náklady: 137 200 €